Fire Rated Construction Details

Note: Prior to any firewalls being constructed it is essential that the builder consults with the project certifier to ensure that the certifier is aware of the firewall construction procedures and the certifier deems the installer competent.

Fire Resistance Level (FRL) is assessed by three performance measures:-

Structural Adequacy / Integrity /Insulation eg 90/90/90

FRL – 90 Mins. & External Fire Source

CSIRO Full-Scale Fire Test FS 3685/2695 has proven that the QT EcoSeries Wall System (shown right) is capable of achieving a fire resistance of 113 minutes Integrity and 115 minutes Insulation when tested in accordance with AS1530.4. Therefore for the purpose of Building Regulations in Australia, the QT EcoSeries Wall System achieved a fire resistance level (FRL) of 90/90/90. The FRL is applicable for exposure to fire source from the tested side (QT EcoSeries Wall Panel side).

Fire Test – FS3685-2695————– Specimen – Typical Cross Section Fire Rated Vertical Control Joint———— Fire Rated Horizontal Control Joint————

FRL – 90 Minutes

To achieve a 90 minute Fire Rating the wall must be constructed so as the wall consists of two layers of 13mm thick fire resistance plasterboard affixed to the timber frame internally and one layer of fire resistant building foil, one layer of 50mm QT EcoSeries Wall Panel with a 5-8mm render applied with finish, affixed directly to a 20-50mm battened out cavity. This system would be capable of achieving Fire Resistance Levels of -/90/90 for Non Load Bearing walls and 90/90/90 for Load Bearing Walls designed in accordance with AS1684 for fire exposure from either direction if tested in accordance with AS1530.4

90 Minute Fire Rated Wall

Extended Wall Areas

The Fire Resistance Levels of 60 & 90 minutes would still apply to the same system extended in height in modular form provided that the structural members are designed in accordance with the relevant structural design code for the height and load of actual installation and an approved joint system appropriate to the FRL and the width of the gap is used for the horizontal and vertical joints in a manner as detailed in the attached drawings.

find out more

Jan 11

QT Finishing

Service

Ensure service pipes and wires are fixed or checked into the frame and not laid loose in the extended wall cavity. All materials that are susceptible to deterioration due to plasticiser migration must be protected (check with product manufacturer). Some PVC products or electrical cabling that penetrate the coating system and QT EcoSeries Wall Panel, require a conduit to ensure it is protected. Copper pipes require a sleeve, conduit or tape to prevent contact with the wall panel.

Penetrations

Voids or gaps created by service penetrations through the exterior wall require weatherproofing and or waterproofing. A common method is to inject with expandable polyurethane foam and seal with a long lasting exterior gap sealant to make a weather tight seal. Where practical add a flange or decorative feature over the hole or penetration.

Sealants

Use an exterior grade weatherproof sealant for exterior wall construction and as a general-purpose gap filling. Apply sealant in accordance to manufacturers recommendations. For a sealant to work effectively, the sealant must be applied as shown in the sketch below, Opening Width (D) x Depth (D/2) half the width. Use backing rod as required. Ensure surfaces are in good condition clean and free from oil, dust, loose materials including old sealant and release agents. Apply masking tape to surfaces where contact with sealant is not required. Tape should be removed before sealant cures. Smooth the surface of the sealant and ensure excess sealant is removed. Refer manufacturers curing or drying times before painting.


Heavy & Frequently Adjusted Fixtures

Heavy items are not to be fitted directly to the QT EcoSeries Wall Panel. They should have their own stand-alone supports or be tied to the supporting wall frame (eg. Clothes lines). Items subject to frequent handling (e.g. Flood-Lights and sensors) require a mounting plate, to be fixed across at least two or more frame studs to give longterm fixing support. The backing plate must be of a material that will offer, long-term weatherproof durability. If the internal lining is
already installed, the mounting plate can be installed externally prior to the installation of the QT
EcoSeries Wall Panel.